Our extensive experience within the Healthcare sector, and working in live environments, enabled us to secure the complex refurbishment of an Emergency Department whilst still remaining in operation 24/7. The proposed works included provision of 5nr Assessment Bed Bays with Staff Base along with another 2nr Assessment rooms in another location within the department and 4 support rooms.
 
This project was completed during the extremely challenging pressures of the pandemic. We worked alongside the Stakeholders to workshop the design, with our in-house team, to meet all the requirements and also provide a bright and productive space for the Trust within 10 weeks. This is a fantastic testament and example to the delivery team at Marcon and a huge complement to our committed supply chain which allowed us to complete the works without any delays caused as part of the Pandemic by materials or labour shortages.

Sector

Healthcare

Duration

10 Weeks

Contract

JCT Design & Build Contract 2016

Value

£700k

Client